Wastewater treatment plant in Maçanet
-
Girona
The construction work will be executed on the plot adjacent to the current Maçanet de la Selva wastewater treatment plant on Puigtió industrial estate. The site is bordered to the south by the rest of the agricultural plot, to the east by La Torderola stream, to the west by Indústria Street and to the north by the current WWTP.
Main activities:
- Diversion of affected watercourses.
- Water line: the two inlet collectors (industrial estate Ø400 mm and urban area Ø630 mm).
- Sludge, flotation, drainage and emptying lines.
- Reagent, air, and deodorization lines: Control facility and treated water tank.
- Electrical, automation and control, ventilation and air conditioning systems.
- Exterior development, auxiliary services, landscaping and finishes.