Combined cycle 1.200 MW power station, Maasbracht
-
The Netherlands
The project consists of prefabricating piping, mechanically assembling BOP (Balance of Plant) equipment, assembling piping in the BOP and Power Island, thermal insulation, and painting. The scope of the work involves the assembly of 392 tons of equipment, the prefabrication of 631 tons of piping, and the assembly of 2,280 tons of piping, valves, and brackets.