Dismantling electromechanical equipment
-
Badalona
The scope of maritime work runs from the Levante sewer to the seawater intake heads.
Main measurements:
Sant Adrià 3 420 m 210 m 35 units 70 units
Sant Adrià 1-2 768 m 192 m 32 units 128 units
Badalona I 432 m 144 m 36 units 72 units
Badalona II 720 m 144 m 18 units 108 units
Demolition of pump buildings in Badalona 1 and Sant Adrià 1 and 2.
The main works to be carried out on each of the jetties are:
- Dismantling pipelines.
- Dismantling benches.
- Dismantling slabs.
- Dismantling longitudinal beams (Badalona I and II).
- Dismantling lintels.
- Removing piles.
- Final site clean-up.
- Demolition and disposal of all material in tanks.